How much will this cost?
In 2026, Council approved $290,000 from the 2026 Capital Budget for the construction of a fifth ball diamond at Sterling Industries Sports Park. The original budget was based on developing a diamond similar to the four existing diamonds already within the park that are geared more towards fastpitch and slo-pitch.
In further discussions with Blackfalds Minor Ball, it was requested to increase the size of the baseball diamond to a U18-sized diamond which Blackfalds currently does not have; subsequently increasing the initial budget for this project by an estimated $120,000 (taken from Capital Reserves)
In total, the project is estimated to cost $410,000.